ASSISTANT ENGINEER (CIVIL) IN FISHERIES DEPARTMENT (DEC 2021) ADVT DATE: Decemember, 2021, Date of Examination: 29th March, 2025

Paper #3063 · 29-03-2025 · 2 reviewed questions

Close paper

Accuracy note: This is a reviewed structured rendering of an official previous-year paper and may cover only part of it. Where available, explanatory notes describe unresolved source or answer issues without supplying a scoring answer. Official examination authority notices remain final.

  1. Paper #3063, Series I, Q156: If the completion time of a particular project is 20 weeks and its earliest expected time is 22 weeks, then slack time for the project is. Options: A 2 weeks; B -2 weeks; C 0; D None of the above.
  2. Paper #3063, Series I, Q166: The water that contains substances which are undesirable or unfit for domestic use is called. Options: A potable water; B contaminated water; C polluted water; D sewer water.